He new Jorge Chávez airport will begin operations starting in December 2024, announced Lima Airport Partners (LAP), operator of the air terminal.

Only at the end of 2023, the works were 70% complete, where the first boarding gates, the state-of-the-art baggage system, the vehicular access viaduct, as well as the beginning of paving of parking areas and roads were implemented. of access.

It is important to note that the project to expand the first airport in Peru to At the beginning of 2025, it will have the capacity to serve 30 million passengers annually.

“The new single passenger terminal will mark a milestone in the region’s airport infrastructure and will mark the start of operations of the first airport city in South America,” said Bill Fullerton, project director.

In addition, the new control tower and the second runway have already been opened last April; In this way, it is possible to manage more than 14,000 flights and mobilize more than 2 million Peruvian and foreign passengers.

When will the Callao Logistics Park open?

For the first quarter of 2024, the Callao Logistics Park, the first commercial project of the new Jorge Chávez airport city to be implemented, will begin operating. For its construction, which began this year, third-party investments exceed US$300 million; Thus, they will contribute to economic development and job creation.

Apart from this infrastructure, in 2023 construction of the following works was also awarded and began: a hotel complex developed by Costa del Sol (two 3 and 5 star hotels), the new southern loading zone operated by IKSA, a new plant of fuel that will triple its storage capacity, a new parking lot operated by Los Portales Estacionamientos with greater capacity, among others.